Construction progress

Progress as of 03 June 2015

  Description % Completion
(A) Building and System Works  
1 Main Contract - Basic Reparation and Renovation  
1.1 Space Clearance and Preparatory Work 100%
1.2 Building Repairs and Architectural Work 90%
1.3 Electrical and Communication Works 100%
1.4 Sanitary and Fire Protection Works 95%
1.5 Air Ventilation and Air Conditioning System 95%
1.6 Overheads and Profit 100%
1.7 Discount after Price Negotiation 100%
1.8 VAT 7% 100%
2 Post-Survey Additional Work  
2.1 Extension of Chilled Pipes to Cover the Full Space 100%
2.2 Re-Insulation of Chilled Pipes 100%
2.3 Leaked Roof Replacement and Gutter Repairs 100%
2.4 Office wall demolishing and floor repairing (room 217) 100%
2.5 Office wall, ceiling and lighting works (room 217) 100%
2.6 Original AHU Room Converted into a Multimedia Room 100%
2.7 Installation of Ceramic Floor in the Multimedia Room 100%
2.8 Wall Installation of Multimedia Training Room 100%
2.9 Installation of Pantry Room wall skirting 100%
2.10 Renovation of Existing Tiolets 100%
2.11 Sound-Proof Wall and Ceiling in Teleconference Room 100%
2.12 Additional doors, windows and Locks 95%
2.13 New Sanitation Ware 100%
2.14 Drinking Water Machines 70%
2.15 Replacement of Second Floor Carpet 90%
2.16 Wall Finishing of Second Floor Pantry 30%
2.17 New Service Openings of Ceiling 100%
2.18 New Curtain Rail in Second Floor Training Room 100%
2.19 Installation of Acrilic Sunlight Roof (1.525 m X 1.525 m) 100%
2.20 Basic Signage 30%
2.21 Installation of built-in furniture 30%
2.22 Access control Repair Work 100%
2.23 Additional Work of Electrical System 100%
2.24 Additional Work on Water System 100%
2.25 Additional Work on Air-Conditioning System 100%
2.26 Management Fee and Profit 79%
2.27 VAT 7% 79%
3 Operational Hardware and Software  
3.1 Repair of 2 Elevators 100%
3.2 Installation of New Access Control System 100%
3.3 All Movable Furnitures 100%
3.4 CCTV 100%
3.5 LAN Cables and Wiring 100%
3.6 AP & Licenses for Controller and Wireless System 100%
3.7 UPS and switches for LAN and Internet Systems 100%
3.8 Contingencies 100%
4 Design and Consultant Fees  
4.1 Design Fees for Architects and System Engineers 100%
4.2 Consulting and Construction Supervision Fees 50%
(B) Digital Equipments  
1 Computer PC 46 sets 0%
2 Flat monitor TV for presentation 17 sets 0%
3 Multimedia sets in the Multimedia classroom and Teleconferrence rooms 30%
(C) Landscape  
1 Landscape in the South and Eastern Sides of the Library 0%
(D) Interior Decoration  
1 Exhibition Hall at the Entrance 0%
2 Wall Surface and Graphic Sign 0%
3 Reading Zone on the Second Floor 0%
4 Curtains 0%
5 Signage System 0%
6 Overall Acoustic and Sound Proof in the Library 0%
7 Sound-Proof Wall in Meeting and Teleconference Rooms 0%
8 Toilets for the Disables 0%
9 Design/Management/Supervising Fees 60%
10 VAT 7% 0%
(E) Optional Works (Subject to Available Donor Support)  
1 Open-air Reading Garden Space  
1.1 Space Clearance in Central Court 0%
1.2 Installation of Tress and Plants 0%
1.3 Semi-transparent Roofing System (Partial) 0%
1.4 Outdoor Furniture 0%
1.5 Reinstallation of Drainage System 0%
2 Installation of Roof-top Solar System 0%
3 Library RFID System 0% 
4 Returned Book fetching Robots 0%

 

Pictorial update of the library construction

Following pictures are taken during 06 February 2015. Under the leadership of President Prof. Worsak Kanok-Nukulchai the AIT Library Modernization is underway. The following pictures will display the work in progress of the AIT Library.